430 tons goes underground. Construction of Poland's longest tunnel is getting closer
Under Łódź, the 430-ton cutting head of a TBM machine has been lowered into an underground chamber. In spring 2027, the machine is due to begin boring the 4.6-kilometer tunnel of the High-Speed Rail line.

Ricardo Gomez Angel · Unsplash License
- 0views
- 0likes and saves
- 0skips
In brief
- A head of the TBM machine weighing about 430 tonnes has been lowered into the launch chamber near Łódź.
- Boring of the 4.6-kilometre tunnel of the High-Speed Rail line is to start in spring 2027, and construction works are to be completed in 2029.
- The value of the investment is estimated at more than PLN 2 billion to PLN 2.2 billion, and the tunnel is to be the first element of the railway "Y".
The heaviest element of the machine in the launch chamber
Under Łódź, in the launch chamber of the High-Speed Rail tunnel, a head weighing close to 430 tonnes has been placed. It is the heaviest fragment of the TBM machine, and its positioning requires millimetre precision (Wielkie drążenie pod miastem. Przy sąsiednim tunelu zaczęły się walić kamienice – Portal Samorządowy). Earlier, a shield weighing more than 400 tonnes was placed in the same chamber, and the operation itself lasted several hours (Łódź szykuje się na kolejową rewolucję. Rusza budowa tunelu KDP – Bankier.pl).
Tunnel and schedule
The machine is to begin boring in spring 2027. The route is 4.6 km long and runs from Retkinia towards Łódź Fabryczna railway station (430 ton trafia pod ziemię. Coraz bliżej budowy najdłuższego tunelu w Polsce – WNP.pl). Construction works are to be completed in 2029.
Cost and significance of the investment
The value of the tunnel is given as somewhere between more than PLN 2 billion and PLN 2.2 billion (Wystartowała budowa tunelu CPK pod Łodzią. 9 grudnia poznamy oferty na terminal w Baranowie – Puls Biznesu) (Rusza budowa kolejowego „igreka”. Tunel pod Łodzią powstanie za 2,2 mld zł – Rzeczpospolita). Piotr Malepszak, the government plenipotentiary for CPK, called the investment a breakthrough for the region and described it as the first element of the railway "Y", i.e. the line connecting Warsaw, Wrocław and Poznań. The tunnel is to enable travel from Łódź towards Poznań.
The whole machine and assembly
The entire machine weighs about 4 thousand tonnes and is 130 m long. Its assembly in the launch chamber is under way in the coming weeks.
What's next
In parallel with the works under Łódź, CPK is reviewing the documentation before the construction of the airport, in order to coordinate subsequent works more efficiently. Offers for the terminal in Baranów are to be opened on 9 December.
Sources
- [1]
430 ton trafia pod ziemię. Coraz bliżej budowy najdłuższego tunelu w Polsce· WNP.pl - [2]Łódź szykuje się na kolejową rewolucję. Rusza budowa tunelu KDP· Bankier.pl
- [3]Wystartowała budowa tunelu CPK pod Łodzią. 9 grudnia poznamy oferty na terminal w Baranowie· Puls Biznesu
- [4]
Rusza budowa kolejowego „igreka”. Tunel pod Łodzią powstanie za 2,2 mld zł· Rzeczpospolita
- [5]
Wielkie drążenie pod miastem. Przy sąsiednim tunelu zaczęły się walić kamienice· Portal Samorządowy
Discussion0
- No comments from this perspective yet. Be the first.