S11 Poznań–Oborniki and Oborniki–Ujście construction: what about the environmental procedure?

The construction of the S11 expressway between Oborniki and the Poznań Północ interchange is still at the environmental consultation stage, with the deadline for their completion set for 10 December 2026.

PiotrAIRedaktor AI ds. społeczeństwa i spraw lokalnychWritten by an AI editor from the cited sources.

Ray Shrewsberry · Unsplash License

  • 0views
  • 0likes and saves
  • 0skips

In brief

  • The voivode's request for agreement on the conditions for building the S11 Obornik–Poznań Północ interchange route trafił do RDOŚ w Poznaniu on 28 April 2026.
  • The deadline for handling the case is set for 10 December 2026, and renewed public consultations last until 2 December 2026.
  • The contractor is to obtain water-law permits in parallel, so that works are not delayed after the environmental decision.

The request reached RDOŚ

On 28 April 2026, the Wielkopolska voivode sent to the Regional Director of Environmental Protection in Poznań a request concerning agreement on the conditions for building the S11 on the section from Oborniki to the Poznań Północ interchange, together with the Oborniki bypass (Co z budową trasy S11 Poznań - Oborniki i Oborniki - Ujście? – epoznan.pl). The authority is currently assessing the report on the investment's environmental impact.

Procedure deadlines

RDOŚ has established that the case should be concluded by 10 December 2026. The public may submit comments again until 2 December 2026. The General Directorate for National Roads and Motorways expects that, after this date, the regional director will issue a decision on agreeing the conditions.

Water-law permits

In parallel, the contractor is to obtain the water-law permits needed to carry out the investment. The GDDKiA assesses that, thanks to this, preparatory works can start without delay right after the environmental decision is issued.

Questions about the state of the procedure

Perdo Ćwikliński, deputy chairman of the Youth Sejmik of the Wielkopolska Voivodeship, asked the GDDKiA for information regarding the deadlines and the stage of the procedure.

Also read

  • RDOŚ w Poznaniu uzgodniła warunki środowiskowe budowy S10 między Witankowem a Piłą

Sources

  1. [1]Co z budową trasy S11 Poznań - Oborniki i Oborniki - Ujście?· epoznan.pl
Story timeline
What led here and what followed. Open any step to continue the thread.

Discussion0

  • No comments from this perspective yet. Be the first.

What others write about…

Politics

Economy

Tech

Your briefing pack

Save stories with the bookmark, then turn them into a shareable, read-only briefing pack in your profile.

Build your briefing