PKP PLK announce tender for Jastrzębie-Zdrój line. Poland's largest city without rail returns to the map
Rail is set to return to Jastrzębie-Zdrój, and PKP Polskie Linie Kolejowe has launched a tender to rebuild this connection. The contract value is estimated at PLN 270 million net, with work due to be completed in 2030.

Johannes Plenio · Unsplash License
- 0views
- 0likes and saves
- 0skips
In Brief
- PKP Polskie Linie Kolejowe announced a tender for the reconstruction of the railway connection to Jastrzębie-Zdrój as part of the Kolej Plus program.
- The estimated value of the contract is 270 million PLN net, offers can be submitted until December 4, and the works are expected to be completed by the end of 2030.
- The connection is expected to allow travel from Jastrzębie to Katowice in up to 60 minutes, and ultimately the construction of 20 km of high-speed line would shorten it to about 35 minutes.
- The reconstruction of the nearly 9-kilometer section through mining areas is a challenge, the contractor will have two months for preparations and 20 months for the works.
Tender under Kolej Plus
PKP Polskie Linie Kolejowe announced a procedure for the reconstruction of the connection to Jastrzębie-Zdrój as part of the government program Kolej Plus (PKP PLK announced a tender for the line to Jastrzębie-Zdrój. It is the largest city without a railway in Poland – Puls Biznesu). In this program, the order includes a route leading from Jastrzębie to Żory, and a section connecting Żory with Orzesze, located on the line running from Rybnik to Katowice, has also been designated for reconstruction.
Estimates and deadlines
Deputy Minister of Infrastructure Piotr Malepszak stated at a press conference in Żory that the estimated value of the contract is 270 million PLN net (This is the largest Polish city without a railway. The tender heralds changes – RMF24). The submission of offers will end on December 4, and the ministry along with PLK expects their opening at the beginning of that month. The works are to be completed by the end of 2030.
Goal: one hour to Katowice
As Malepszak announced, the journey from Jastrzębie to Katowice is expected to take no longer than one hour. Ultimately, the construction of the first 20 kilometers of high-speed line from Katowice towards Żory and Rybnik is also planned, which would shorten the travel time of regional fast trains to about 35 minutes.
Difficult construction conditions
According to Marcin Mochocki, a member of the management board of PKP PLK, the reconstruction of the connection poses a challenge for the company in Silesia. The contractor will have two months for preparations, and the actual works are expected to last 20 months. The nearly 9-kilometer section runs through mining areas with difficult geology, and a complex engineering structure will be built over the mining reservoir along the route.
Sources