Regional Environmental Protection Directorate in Poznań approved environmental conditions for the construction of the S10 expressway between Witankowo and Piła
The Regional Environmental Protection Directorate in Poznań has closed the final stage of consultations before issuing a permit for the construction of the S10 expressway on the Piła–Witankowo section. Work on this section is scheduled to be completed by July 2028.

Ray Shrewsberry · Unsplash License
- 0views
- 0likes and saves
- 0skips
In brief
- The Wielkopolska voivode has received the environmental conditions for the S10 expressway section Piła–Witankowo, agreed by the Regional Directorate for Environmental Protection (RDOŚ) in Poznań.
- This is the last document needed before the building permit can be issued.
- Completion of works on this section is planned for July 2028, and construction is delayed by at least six months.
The last document before the permit
The Wielkopolska voivode has received from the Poznań RDOŚ the agreed environmental conditions for the S10 expressway between Piła and Witankowo (Budowa S10. Ostatnia prosta do pozwolenia na budowę – asta24.pl). This document was the last one missing before the permit to carry out the investment could be issued. The permit may be issued still this month, and at the latest next month.
Delays and timeline
Construction is already delayed by at least six months. Completion of works on this section is planned for July 2028. Until now, contractors have been waiting solely for the permit that will allow the actual works to begin.
Significance for the region
For drivers and residents of northern Wielkopolska, this means the investment is moving from the planning stage to implementation (Piła: Zielone światło dla S10 na odcinku Witankowo - Piła – informacje.wp.pl). Local media note that the new road is expected to improve connections in the region (Zielone światło dla S10 na odcinku Witankowo – Piła! Jest ważna decyzja RDOŚ – pila.pl).
What's next
Environmental agreement is a condition for starting works, but it does not complete the whole process. The decision on the permit will be made by the voivode, and only after that can construction begin.