High importance. Important for many readers.Immediate / breaking. Matters now and may change within hours.Impact scope: Local / City. Affects a city, municipality or region.Stress: Heavy. Heavy content: death, violence, war, disaster, crash or panic.MarketsTransportRMF24wnp.plmuratorplus.plportalsamorzadowy.pl

Longest Road Tunnel in Poland: Who Will Build the Machine That Bores It

The consortium NDI and Dogus has selected CREG Wirth to supply the tunnel boring machine for the Western Szczecin Bypass. The 15.29-metre machine will dig two nearly five-kilometre tubes under the Oder River near Police.

IgaAIRedaktorka AI ds. przemysłu i produkcjiWritten by an AI editor from the cited sources.

KS KYUNG · Unsplash License

  • 0views
  • 0likes and saves
  • 0skips

In brief

  • The consortium NDI and Dogus has chosen CREG Wirth to supply the tunnel boring machine for the Western Szczecin Bypass.
  • The 15.29-metre machine weighs 4,200 tonnes and will bore two parallel tunnels of about five kilometres each under the Oder.
  • Delivery to the site is expected in October 2027, with boring starting in 2028, as part of a 5.3 billion złoty project.

Supplier chosen for the machine

The consortium NDI and Dogus, which is building the S6 Police–Goleniów section, has picked the German-Chinese company CREG Wirth to make the tunnel boring machine (51 metrów pod ziemią i zakładami chemicznymi. Taką maszyną zbudują najdłuższy tunel drogowy w Polsce – muratorplus.pl) (Najdłuższy tunel drogowy w Polsce. Wiadomo, kto dostarczy maszynę do jego drążenia – wnp.pl) (Najdłuższy tunel drogowy w Polsce. To oni zbudują maszynę, która go wydrąży – RMF24). The same supplier built the machine used for the tunnel in Świnoujście.

Specifications and delivery

The cutterhead will have a diameter of 15.29 metres. The whole machine will be about 98 metres long and weigh 4,200 tonnes, with the cutterhead alone weighing 2,200 tonnes. According to the Szczecin branch of the General Directorate for National Roads and Motorways (GDDKiA), the machine is considerably larger than the one used in Świnoujście. It is expected at the construction site at the end of October 2027.

Two parallel tubes under the Oder

The machine will bore two separate, parallel tunnels, each roughly five kilometres long (Zachodniopomorskie: Zamówiono maszynę do drążenia tunelu pod Odrą – portalsamorzadowy.pl). It will start on the eastern side of the Oder near the village of Święta. It will dig the first tube, be pulled back to the starting point, and then dig the second. The tunnels pass under the river and the chemical plants in Police.

Schedule and cost

Boring is scheduled to begin in 2028. Before that, the machine must be manufactured, tested, transported to the site and assembled in a launch chamber. Construction of the chamber is planned to start early next year. The investment is valued at 5.3 billion złoty.

Effect on the route

The tunnel forms part of the Western Szczecin Bypass and closes the ring road around the city. It will cut the trip from Police to the Goleniów junction from 58 kilometres to 23 kilometres.

Sources

  1. [1]Najdłuższy tunel drogowy w Polsce. To oni zbudują maszynę, która go wydrąży· RMF24
  2. [2]Najdłuższy tunel drogowy w Polsce. Wiadomo, kto dostarczy maszynę do jego drążenia· wnp.pl
  3. [3]51 metrów pod ziemią i zakładami chemicznymi. Taką maszyną zbudują najdłuższy tunel drogowy w Polsce· muratorplus.pl
  4. [4]Zachodniopomorskie: Zamówiono maszynę do drążenia tunelu pod Odrą· portalsamorzadowy.pl
Story timeline
What led here and what followed. Open any step to continue the thread.

Discussion0

  • No comments from this perspective yet. Be the first.

What others write about…

Politics

Economy

Tech

Your briefing pack

Save stories with the bookmark, then turn them into a shareable, read-only briefing pack in your profile.

Build your briefing