Eleven bids in tender for design of Oświęcim bypass expansion
The Kraków branch of GDDKiA has received 11 offers for designing the expansion of a 2.3-kilometre section of the Oświęcim bypass. The cheapest bid comes in below the agency's budget, while a much higher offer tops the list.


In brief
- GDDKiA received 11 bids for designing the expansion of a 2.3-kilometre section of the Oświęcim bypass.
- The cheapest offer, from KLOTOIDA at 1,693,710 zł, is below the 1.9 million zł budget.
- About 18,000 vehicles use the road daily, and construction is planned for 2032–2034.
Eleven firms bid for the design contract
The Kraków regional office of the General Directorate for National Roads and Motorways (GDDKiA) opened bids on 17 November 2026 in a tender for preparing design documentation for expanding the Zatorska and Chemików streets in Oświęcim and Zabórze. Eleven companies submitted offers, and the agency has started analysing them (GDDKiA: jedenaście ofert na projekt rozbudowy obwodnicy Oświęcimia – portalsamorzadowy.pl).
Price spread between offers
The lowest bid came from Pracownia Inżynierska KLOTOIDA at 1,693,710 zł. It is the only offer that fits within GDDKiA's budget of 1.9 million zł (18 tys. aut dziennie i tylko po jednym pasie. Oświęcim szykuje rozbudowę ważnej drogi – motoguru.pl). The second-cheapest bid, from IVIA, came in at 1,968,000 zł, which is 68,000 zł above the amount the contracting authority had set aside. The most expensive offer, from Egis Poland, sits at the other end of the range, and the gap between the cheapest and dearest proposals is substantial.
Scope of the project
The 2.3-kilometre section links the new city bypass with the Telki roundabout. Around 18,000 vehicles travel this route each day, and it has only one lane in each direction (18 tys. pojazdów dziennie i tylko jeden pas. GDDKiA planuje przebudowę – msn.com). The planned investment aims to ease traffic on one of the most heavily loaded roads in Oświęcim.
Construction timeline
The design work is only the first step. Construction is currently planned for 2032 to 2034, so drivers will have to wait several years before any physical changes begin. Reports also note that the route itself may change, with a completely new alignment under consideration.
Sources
- #GDDKiA
- #OświęcimBypass
- #RoadTender
- #Zatorska
- #Chemików
- #TelkiRoundabout
- #Route44
- #Oświęcim
- #Bypass
Story graph
Connected stories
Eleven bids in tender for design of Oświęcim bypass expansion
The Kraków branch of GDDKiA has received 11 offers for designing the expansion of a 2.3-kilometre section of the Oświęcim bypass. The cheapest bid comes in bel…