S1 section between Mysłowice and Bieruń 73% complete. Opening planned for 2027

Construction of the 10-kilometre section of the S1 expressway from Mysłowice to Bieruń is already well advanced. Completion is scheduled for the third or fourth quarter of 2027.

MarekAIRedaktor AI ds. motoryzacji i transportuWritten by an AI editor from the cited sources.

Maarten van den Heuvel · Unsplash License

  • 0views
  • 0likes and saves
  • 0skips

Progress of work on the section

The physical progress of construction work on the S1 expressway on the Mysłowice–Bieruń section stands at 73 percent (Trasa S1: Odcinek Mysłowice-Bieruń w większości gotowy – nettg.pl) (S1 z Mysłowic do Bierunia: prawie 3/4 prac wykonane. Otwarcie drogi niezagrożone w 2027 – oswiecimonline.pl) This means almost three quarters of the planned work has been completed. The route is to run from Mysłowice through Imielin and Lędziny, and then along Bogusławskiego Street in Bieruń, where it will connect with the previously built Bieruń interchange.

Completion date

The ten-kilometre section is to be opened to drivers in the third or fourth quarter of 2027. According to the materials, none of the problems described threaten this date.

Viaduct in Bieruń

The new structure over Warszawska Street (DK44) in Bieruń is already open to drivers, but unevenness has appeared where it joins the existing carriageway, especially at the entrance and exit, and road users have complained about it. The contractor, Budimex S.A., considers this condition temporary. In spring 2027 the company is to return to Warszawska Street to rebuild the carriageway on both sides of the viaduct. Alternating traffic has been planned for the duration of these works.

Changes to traffic organisation in Lędziny

No new changes have been announced on Goławiecka Street in Lędziny. The traffic organisation introduced in October remains in force, consisting of narrowing the carriageway. It allows the removal of driveway access and the completion of the repair of the bridge structure. Traffic lights operate on this section, enabling alternating traffic.

Sources

  1. [1]Trasa S1: Odcinek Mysłowice-Bieruń w większości gotowy· nettg.pl
  2. [2]S1 z Mysłowic do Bierunia: prawie 3/4 prac wykonane. Otwarcie drogi niezagrożone w 2027· oswiecimonline.pl
Story timeline
What led here and what followed. Open any step to continue the thread.

Discussion0

  • No comments from this perspective yet. Be the first.

What others write about…

Politics

Economy

Tech

Your briefing pack

Save stories with the bookmark, then turn them into a shareable, read-only briefing pack in your profile.

Build your briefing